Location: Oklahoma City, Oklahoma
Fleet type: Light-duty electric vehicles
Narrative
The Oklahoma City Zoo has worked with Central Oklahoma Clean Cities and its host organization, the Association of Central Oklahoma Governments (ACOG), on numerous projects to help improve the Zoo’s vehicle fleet, improve efficiency, and reduce emissions. The Zoo has been more willing than most fleets to take a chance on alternative fuels and look for ways to improve its sustainability.
In 2024 the Zoo was awarded $282,096 from ACOG’s Public Fleet Grant Program. Their application included purchasing two electric vehicles (EVs) to replace older gas vehicles in their fleet as well as installing Level 2 EV chargers that are powered by a solar carport canopy. The two EVs are the first light duty EVs the Zoo has incorporated into their fleet. They did have Level 2 charging in the public parking lot for many years and have had a good experience with keeping them operational.
Conservation and practicing environmentally friendly practices are ingrained in the Oklahoma City Zoo’s mission. Their organization was inclined to be more interested in EVs for the environmental benefits of being quieter while driving, as well as being emissions free. The solar canopy was a priority for the Zoo. They wanted to incorporate it into the charging to provide free renewable fuel for their new EVs as well as supplemental power to their administrative headquarters building.
Building off the success of their first solar powered level 2 EV charger as well as the EVs, the Oklahoma City Zoo decided to apply for ACOG’s 2026 Public Fleet Grant. In their most recently awarded application they decided to build a much larger solar carport in their public parking lot. This will be a 174.4 kW system that is estimated to produce 239,115 kWh each year, which is the equivalent of mitigating 186.6 tons of CO2 annually (based on the area electric grid mix). The system will power four Level 2 chargers, capable of charging eight EVs at the same time. When power is not used for the EV chargers, extra energy will be sent to mitigate some of the Zoos overall electrical use.
Being in a parking lot demonstrates to the public the power of solar and EV charging. It will be a model for others to see the benefits of going electric. A rendering of what it should look like when finished is shown below.
The project is currently in progress, and the Zoo plans to provide free EV charging to visitors. They are building off the success of their first three EV chargers that are free for visitors. “Those chargers are typically in use during the day. It’s rare to see them available,” says Rebecca Snyder, Oklahoma City Zoo Sustainability Manager. “We decided we wanted to provide more charging that is free for our visitors to encourage more people to visit the Zoo.”
We discussed potential issues with providing free charging, but given their years of success with free charging they wanted to continue this path.
Other communities and cities are noticing the projects at the Zoo. ACOG regularly hosts public meetings for member communities and talks about current projects. The Zoo solar EV carports are of high interest as other cities wanted to emulate the success. Coupling EV charging with free renewable energy from solar panels that also shade cars is a compelling combination. The additional supplemental power when the chargers are not in use is a great benefit as well to mitigate against rising electrical costs. The big question is what is the typical payback period for installing solar power EV chargers. For the Zoos canopies it will take a few years, however they are quick to mention that they have never had a “payback period” before with other types of refueling equipment.
Outputs & Outcomes
Solar and EV charging is a powerful combination in Oklahoma. With ample sunny days powering EV with renewable and free energy accelerates the payback period of purchasing a more expensive EV over a conventional gas vehicle. Both of their EVs are operating daily and have become the vehicles of choice for Zoo employees. The EVs are so sought after that the Zoo Executive Director typically uses an EV for his daily work. Because of this success they are planning on adopting more EVs into their fleet with longer plans of phasing out gas vehicles entirely.
Best Practices & Lessons Learned
The biggest challenge with this project was scoping out the solar canopy with the EV charging. Because the canopy was custom designed and built it inflated costs a bit from the original budget estimate. With the second solar canopy the same company is working to install them for the Zoo and they have a much better handle on costs and estimates. Things always change in construction, however both parties feel more confident in the estimates and think they can stay within budget a little easier than the first project – despite the second project being much larger in scale.
PDF Version