Location: Mustang, Oklahoma
Fleet type: Light-duty EVs and Fast Charging
Narrative
The City of Mustang is a thriving suburban community just outside of the Oklahoma City city limits, with a population of around 25,000 residents and one of the faster growth rates in the state of Oklahoma. It is an active, middle-class community with a strong sense of civic identity. Unlike some of the other communities featured in Oklahoma fleet success stories, Mustang did not have an established track record with alternative fuels or electric vehicles (EVs) heading into this project. For Mustang, this was a first step and it came with both enthusiasm and skepticism.
The push to explore electric vehicles and EV charging came from within City Hall itself. Staff members, some of whom drive personal EVs, began making the case to City Council that Mustang should start moving in the direction of electrification. They wanted to test the waters, understand the technology, and signal that Mustang was willing to grow alongside its rapidly expanding community. After working with the Central Oklahoma Clean Cities Coalition/Drive EV Oklahoma, the city applied for ACOG’s 2024 Public Fleet Grant and received an award of $274,550 — with the grant covering approximately 80% of the total project cost.
With that funding, Mustang purchased and installed two DC fast chargers at their City Hall complex. The location was a deliberate choice. City Hall sits near the public library and active sports fields, making it a natural gathering point for residents throughout the day. Placing fast chargers there meant they would be accessible and visible to the broader community — not tucked away in a fleet yard, but out in the open where residents could see and use them. The chargers are available to anyone with an EV, including city employees who drive personal EVs and can now charge conveniently while at work.
Unlike some public charging installations that offer free charging, Mustang’s DC fast chargers do carry a usage fee. However, the city was intentional about keeping rates competitive and fair — the goal was never to profit from the chargers, but to offer a reasonable, accessible option for EV drivers in the community without overcharging them for the convenience of fast charging.
Not everyone was immediately on board. Several residents and even some City Council members were skeptical that EV charging infrastructure was the right use of public resources, even with a grant covering the lion’s share of the cost. It was a fair question for a city without a history of alternative fuel investment and without any EVs currently in its own fleet of roughly 100 city vehicles. For Mustang, this project was less about what they had done and more about signaling where they were willing to go.
Early results have offered some encouragement for those who championed the project. Since installation, the chargers have seen steady and consistent use — a bit more than many expected. It is common to see an EV or two plugged in during the day, a modest but meaningful sign that there is real demand in the community for public charging options.
Outputs & Outcomes
Mustang is taking a measured, deliberate approach to electrification. They currently have no EVs in their city fleet, and their posture for now is one of careful observation — watching how the chargers perform, tracking community usage, and gauging whether the appetite exists to expand. That patience is sensible for a smaller city taking its first steps into new technology. What they have done is lay a foundation. The infrastructure is in place, the community is engaging with it, and the conversation about EVs in Mustang has begun in a tangible, visible way.
Best Practices & Lessons Learned
Mustang’s story is a useful reminder that fleet electrification doesn’t have to start with vehicles — sometimes it starts with infrastructure. Installing public fast chargers before purchasing fleet EVs allowed Mustang to dip a toe in the water, build community awareness, and gather real data on local EV demand with relatively low risk, especially with grant funding covering most of the cost. For communities where EV skepticism exists – among residents, council members, and/or staff – starting with public-facing infrastructure provides an immediate, tangible benefit to the community (especially the way it has been implemented in Mustang). It can be a smart way to build the case for deeper investment down the road. Meeting the public where they are, literally and figuratively, is a reasonable first chapter in an electrification story that is still being written.